| Characteristic | Compute | Data centers | Power |
|---|---|---|---|
| - | - | - | - |
| - | - | - | - |
| - | - | - | - |
| - | - | - | - |
| - | - | - | - |
| - | - | - | - |
The chart is not accessible to screen readers. Please switch to the table view to access the data.
Download
Sources
Release date
May 2026
Region
Worldwide
Survey time period
March 2026
Supplementary notes
The source adds the following information: Figures assume that NVIDIA accounts for 75 percent of total compute spend. Uses VR200 (Rubin) chip at USD 80,500 per GPU (including node costs) and 3,000W per package as baseline spec across all years. Assumes 1.2 PUE and USD 15 million per MW for data centers, and USD 2,500 per kW for new power capacity. Figures also assume that 15 percent of required data center space is brownfield in 2026, growing to 30 percent by 2031. Totals may not sum due to rounding.